Projects
From Start to Finish, We Take Care of Your Entire Project
“This is by far the largest project we have undertaken”- Team Machine Tools Inc.
Project: To disassemble, transport and install one of the largest Vertical Turning Lathes in the US.
Timeframe: 2022 – 2024. Two years from purchase to final testing
Overview: L&H Industrial is a global company that provides solutions for heavy industries, offering design, engineering, manufacturing, monitoring, and maintenance services for some of the biggest machines in the world.
Project Highlights:
-
Team Machine is contracted by L&H Industrial, headquartered in Gillette, WY, to disassemble, transport and install a 12.8 meter CNC Vertical Boring Machine from York, PA to Tempe, AZ
-
In September 2023, Team began installation, after L&H built a completely new foundation and related machine guarding and electrical substation
-
Team Machine was responsible for preparing all assemblies and major components for pre-assembly and rigging into the final position within the foundation
-
Installation also included all electrical, piping, hose and fittings connections; fastening, rough leveling and fine adjusting the major components; final laser calibration, hydrostatic pocket clearances, and advisement on emergency stops, crane clearances and parameters
L&H INDUSTRIAL
Tempe, AZ
Installation of a 12.3 meter CNC Vertical Boring Machine
Niagara Falls, NY
Project: Installation of a Toshiba BF-130B CNC floor type horizontal Boring and Milling Machine
Project Highlights:
-
Skrlin constructed a new foundation for the Toshiba BF-130B CNC
-
Team Machine ensured proper placement of the bed way and rough levelling
-
Large components from locations within the plant were placed by overhead crane to final positions on the foundation
-
All external and internal wiring were connected from the Power Distribution Panel, clearances checked, and gib and wedges fitted
-
Conducted pre start-up checks, powered and moved the machine to begin final alignment and lasering
-
Provided operator training on the Tosnuc 888 control
Skrlin Coating and Blasting Ltd
Siemens Energy
Painted Post, NY
Project: Removal and installation of an Innse Berardi CNC Horizontal Machine Center from Siemens Energy Plant in Duisburg, Germany to Siemens Energy in Painted Post, New York
Timeframe: January 2022-May 2023
Project Highlights:
-
Team Machine dismantled and removed the Innse Berardi CNC Horizontal Machine Centre from Siemens Germany over 5 weeks
-
Siemens packaged and shipped via ocean freight to their plant in New York
-
After a new foundation was complete, Team Machine began to uncrate all components and casting for assembly
-
Modifications were made to many pieces to suit the new foundation and surrounding support equipment, with installation completed in May 2023
Large North East Forging Plant -Tacchi
USA
Project: Installation of a Tacchi machine built in Italy
Timeframe: 2020. Three month installation
Project Highlights:
-
Machine is used for large diameter long heavy shafts or cylindrical workpieces;
-
80" swing with 80 feet between centers
-
Used for large Milling attachments for complex features