top of page
Projects

From Start to Finish, We Take Care of Your Entire Project

​“This is by far the largest project we have undertaken”- Team Machine Tools Inc.

 

Project: To disassemble, transport and install one of the largest Vertical Turning Lathes in the US.

Timeframe: 2022 – 2024. Two years from purchase to final testing

 

Overview: L&H Industrial is a global company that provides solutions for heavy industries, offering design, engineering, manufacturing, monitoring, and maintenance services for some of the biggest machines in the world.

 

Project Highlights:

  • Team Machine is contracted by L&H Industrial, headquartered in Gillette, WY, to disassemble, transport and install a 12.8 meter CNC Vertical Boring Machine from York, PA to Tempe, AZ

  • In September 2023, Team began installation, after L&H built a completely new foundation and related machine guarding and electrical substation

  • Team Machine was responsible for preparing all assemblies and major components for pre-assembly and rigging into the final position within the foundation

  • Installation also included all electrical, piping, hose and fittings connections; fastening, rough leveling and fine adjusting the major components; final laser calibration, hydrostatic pocket clearances, and advisement on emergency stops, crane clearances and parameters

L&H INDUSTRIAL
Tempe, AZ
Installation of a 12.3 meter CNC Vertical Boring Machine

Niagara Falls, NY

 

Project: Installation of a Toshiba BF-130B CNC floor type horizontal Boring and Milling Machine 

Project Highlights:

  • Skrlin constructed a new foundation for the Toshiba BF-130B CNC 

  • Team Machine ensured proper placement of the bed way and rough levelling 

  • Large components from locations within the plant were placed by overhead crane to final positions on the foundation 

  • All external and internal wiring were connected from the Power Distribution Panel, clearances checked, and gib and wedges fitted 

  • Conducted pre start-up checks, powered and moved the machine to begin final alignment and lasering 

  • Provided operator training on the Tosnuc 888 control ​

Skrlin Coating and Blasting Ltd

Siemens Energy

Painted Post, NY

Project: Removal and installation of an Innse Berardi CNC Horizontal Machine Center from Siemens Energy Plant in Duisburg, Germany to Siemens Energy in Painted Post, New York 

Timeframe: January 2022-May 2023

Project Highlights:

  • Team Machine dismantled and removed the Innse Berardi CNC Horizontal Machine Centre from Siemens Germany over 5 weeks 

  • Siemens packaged and shipped via ocean freight to their plant in New York 

  • After a new foundation was complete, Team Machine began to uncrate all components and casting for assembly 

  • Modifications were made to many pieces to suit the new foundation and surrounding support equipment, with installation completed in May 2023 

Large North East Forging Plant -Tacchi 

USA

Project: Installation of a Tacchi machine built in Italy

Timeframe: 2020. Three month installation

Project Highlights:

  • Machine is used for large diameter long heavy shafts or cylindrical workpieces;  

  • 80" swing with 80 feet between centers 

  • Used for large Milling attachments for complex features 
     

Views From The Job Site